12

January 15, 2016 8:15 pm Published by Leave your thoughts

Erection of Drill Floor Sub-structure to sixth generation semi-submersible drilling rig has been completed.

On January 15, 2016 the drill floor was successfully lifted and installed on the rig. The drill floor is located above the moon pool and over the drilling center of the rig. The derrick will be mounted on the drill floor, as well as other drilling equipment such as the drawworks, iron roughnecks, rotary table and drillers control cabin.

Categorised in:

This post was written by rigs_admin